AI Orchestrator

A Specialized and Secure AI Orchestrator for Swiss Financial Compliance

View the Project on GitHub Digital-AI-Finance/wecan-innosuisse-ai-draft

WP1: Project Management

Home > Work Packages > WP1


Overview

Attribute Value
Duration M1-M24 (Full project)
FHGR Hours 400h
Wecan Hours 200h
Total Hours 600h
Lead FHGR Project Manager

Objectives

  1. Establish effective project governance and coordination
  2. Ensure timely delivery of all milestones and deliverables
  3. Manage risks and stakeholder relationships
  4. Provide regular progress reporting to Innosuisse
  5. Facilitate knowledge transfer between partners

Activities

Governance

Coordination

Reporting

Stakeholder Management


Deliverables

ID Deliverable Due Status
D1.1 Project Kickoff Report M1 Complete
D1.2 Q1 Progress Report M3 Complete
D1.2 Q2 Progress Report M6 Complete
D1.2 Q3 Progress Report M9 Complete
D1.2 Q4 Progress Report M12 Complete
D1.2 Q5 Progress Report M15 Complete
D1.2 Q6 Progress Report M18 Complete
D1.2 Q7 Progress Report M21 Complete
D1.2 Q8 Progress Report M24 Complete
D1.3 Stakeholder Engagement Plan M2 Complete
D1.4 Data Management Plan M2 Complete
D1.5 Risk Mitigation Reports Ongoing Complete
D1.6 Final Project Report M24 Complete

All deliverable templates complete. See deliverables/ for detailed templates.


Monthly Breakdown

M1-M4 (Foundation Phase)

Month FHGR Tasks Wecan Tasks
M1 Create repo, draft consortium agreement, kickoff meeting, set up comms Sign agreement, nominate leads, provide company info
M2 First steering meeting, draft D1.4, document GDPR protocols Review D1.4, confirm DPO contact
M3 Prepare Q1 report, update timeline Review Q1 report
M4 Prepare MS1 presentation, compile Q1 deliverables Attend steering committee

M5-M12 (Development Phase)

Month Key Activities
M5 Technology selection support, risk tracking
M6 Q2 report, D1.3 Stakeholder Plan, D1.5 Risk Report
M7-M9 Ongoing coordination, Q3 report
M10-M11 Integration planning, WP4 kickoff support
M12 Q4 report, Innosuisse mid-project review

M13-M24 (Validation Phase)

Month Key Activities
M13-M15 Q5 report, pilot preparation
M16-M18 Q6 report, MS4 coordination
M19-M20 Q7 report, MS5 preparation
M21-M24 Final deliverables, project closeout, D1.6

Governance Structure

                    Steering Committee
                    (Quarterly meetings)
                           |
            +--------------+--------------+
            |                             |
      FHGR Project Lead            Wecan Project Lead
            |                             |
    +-------+-------+             +-------+-------+
    |       |       |             |       |       |
  WP2     WP3     WP4           WP4     WP5    Ops
  Lead    Lead    Lead          Lead    Lead   Lead

Steering Committee

Technical Sync


Risk Management

Risk Categories

Category Examples
Technical Model accuracy, integration issues
Resource Staff changes, capacity constraints
External Regulatory changes, partner issues
Data Document quality, availability

Risk Process

  1. Identify: Weekly risk review in technical sync
  2. Assess: Likelihood x Impact matrix
  3. Mitigate: Assign owner, define actions
  4. Monitor: Track status in risk register
  5. Report: Include in D1.5 Risk Mitigation Reports

GitHub Issue: #448 - Risk Register & Mitigation Tracking


Communication Plan

Channel Frequency Participants Purpose
Teams Channel Daily All team Quick questions, updates
Technical Sync Weekly Tech leads Implementation details
Steering Committee Quarterly Project leads Strategic decisions
Innosuisse Reports Quarterly FHGR Lead Formal progress

Success Metrics

Metric Target
Milestone achievement 5/5 milestones passed
Deliverable completion 19/19 on time
Budget adherence Within 5% of plan
Risk mitigation No critical unmitigated risks
Partner satisfaction Positive feedback

Back to Work Packages Next: WP2