Home > Progress
| Metric | Value |
|---|---|
| Current Month | M3 (March 2026) |
| Project Phase | Phase 1: Foundation (M1-M4) |
| Next Milestone | MS1: Project Foundation (M4 - April 2026) |
| Overall Status | On Track |
| Partner | Planned (Total) | Allocated | Monthly Average |
|---|---|---|---|
| FHGR | 3,500h | 3,497h | ~146h/month |
| Wecan | 2,300h | 2,301h | ~96h/month |
| Total | 5,800h | 5,798h | ~242h/month |
Note: 2h variance results from rounding across 24 monthly allocations.
| Metric | Count |
|---|---|
| Total Tasks (24 months) | 314 |
| Execution Plans Complete | 24/24 |
| Deliverable Templates | 19/19 (Template Ready) |
| Milestones Defined | 5/5 with GO/NO-GO criteria |
| Risk Registers | 72 risks (3 per month) |
Status: GREEN
| Work Package | Planned Tasks | Completed | Status |
|---|---|---|---|
| WP1 | 7 | 7 | GREEN |
| WP2 | 6 | 5 | GREEN |
| Total | 13 | 12 | 92% |
Key Accomplishments:
Status: GREEN
Key Activities:
| Month | Key Activities | Deliverables |
|---|---|---|
| M03 | Q1 Progress Report, WP2 training data preparation | D1.2 (first quarterly) |
| M04 | MS1: Project Foundation - GO/NO-GO decision | MS1 criteria review |
| Report | Period | Link |
|---|---|---|
| M01 Status Report | January 2026 | View |
| M02 Status Report | February 2026 | View |
| Progress Dashboard | Real-time | View |
| Month-by-Month Review | All months | View |
| Phase | Months | Status | Description |
|---|---|---|---|
| Phase 1: Foundation | M1-M4 | Active | Project setup, team onboarding, initial research |
| Phase 2: Core Development | M5-M9 | Planned | Model training, OCR pipeline, document extraction |
| Phase 3: Integration | M10-M13 | Planned | CRM integration, field matching, multi-source fusion |
| Phase 4: Validation | M14-M18 | Planned | Pilot deployments, form pre-filling, testing |
| Phase 5: Finalization | M19-M21 | Planned | Security audit, TRL documentation, scientific papers |
| Phase 6: Completion | M22-M24 | Planned | Benchmark dataset, final reports, project close-out |
Source: Project Status, M01 Report, M02 Report